LIST OF COMPLETED PROJECTS
S-No | Contract No/Title | Brief Description of Project | Client | Contract Value (SR) | Start Data | End Date |
1 | STC/Aces Contract | Rehabilitation of Technical Building | STC/ACES | 18,000,000 | 21-Jun-08 | 20-Sep-09 |
2 | 12/793 | Complete Construction of 19 Classes in School in Habtan Mahael Aseer | Ministry of Education | 1,989,064 | 9-Feb-09 | 10-Dec-09 |
3 | 12/793 | Complete Construction of 19 Classes in School in Ain AL Darab Mahael Aseer | Ministry of Education | 1,989,064 | 7-Feb-09 | 4-Dec-09 |
4 | 31/51 | Complete Construction of Elementary and Secondary School in Hajeef | Ministry of Education | 3,192,075 | 9-Jan-10 | 24-May-11 |
5 | 31/50 | Complete Construction of Elementary and Secondary School in Dhalem | Ministry of Education | 3,236,601 | 31-Oct-10 | 14-Mar-12 |
6 | 59/104 | Construction of Warehouse -Manpower for Electromechanical Works | ACES | 10,945,295 | 21-Feb-11 | 15-Jun-12 |
7 | STC/Aces Contract | Rehabilitation of Technical building 2014 | STC/ACES | 84,419,643 | 3-Aug-14 | 2-Aug-16 |
8 | 003752-1PO | Qurrayah Power Plant QPP-SEC | ACES | 1,394,000 | 16-Feb-16 | 4-Feb-17 |
9 | Aces Contract | Managed Operation & Maintenance of Mobily Electromechanical & TFM | Etihad Etisalat Company(Mobily ) | 67,692,085 | 1-Jan-17 | 31-Dec-17 |
10 | Aces Contract | CW -Excavation, Grading, Construction of boundary wall including labour | Etihad Etisalat Company(Mobily ) | 625,668 | 12-Mar-17 | 3-Feb-18 |
11 | Aces Contract | CW -Excavation, Grading, Construction of boundary wall including la | Etihad Etisalat Company(Mobily ) | 625,668 | 12-Mar-17 | 3-Feb-18 |
12 | Aces Contract | In-Building solution 2017 | Etihad Etisalat Company(Mobily ) | 17,740,000 | 26-Apr-17 | 6-May-18 |
13 | STC/Aces Contract | Rehabilitation of Technical buildings 2017 | STC/ACES | 32,493,300 | 15-Nov-17 | 3-Apr-20 |
14 | Aces Contract | Smart City FTTH - RCY -first phase | Royal Commission for Jubail and Yanbu | 31,773,741 | 17-Dec-17 | 16-Dec-20 |
15 | STC/Aces Contract | O&M and Technical Support Operation for IBS | STC/ACES | 1,880,000 | 20-Nov-17 | 20-Nov-19 |
16 | STC/Aces Contract | Rehabilitation of Technical buildings, Switches & firefighting project 2018 | STC/ACES | 5,192,620 | 01-Aprl-18 | 3-Apr-20 |
17 | STC/Aces Contract | Rehabilitation of Technical buildings, Switches & firefighting project 2019 | STC/ACES | 4,549,057 | 01-Aprl-18 | 3-Apr-20 |
18 | Mobily/Aces Contract | Civil Works under contract #124/2016/ACES | Etihad Etisalat Company(Mobily ) | 754,000 | 7-Oct-18 | 7-Oct-19 |
19 | Aces Contract | Civil work-fence lighting - Trenching | Saudi Chemical Co | 1,667,239 | 22-Nov-18 | 1-Dec-19 |
20 | STC/Aces Contract | Operation TFM project-Site Operational Protection | STC/ACES | 2,005,445 | 4-Aug-19 | 5-Dec-20 |
21 | STC/Aces Contract | Electro Mechanical for network expansions 2020 | STC/ACES | 3,270,844 | 1-Aug-19 | 31-Jul-21 |
22 | STC/Aces Contract | Technical Buildings Rehabilitation 2019 | STC/ACES | 1,992,268 | 1-Aug-19 | 28-Mar-21 |